Presidential submission · September 2026

A sovereign water company. Farming stays with the lessees.

Until programme year 25 the water is taken mainly from Lake Nasser. From that year, seawater desalination is used extensively. By year 13 the old Nile valley irrigation schedule is fully modern. Crop sales stay with the lessees. The company earns a water charge, an 8% royalty and land lease.

The decreeSubmitted for Presidential Decree

Egyptian Mega Agriculture Corporation · Feasibility study G

Water at maturity

94.5bn m³

Wheat, peak year

72 Mt

Exports + import savings

€4.14tn

50 years

Accumulated cash

€28.1bn

Year 50, Charts series

Pipes, pumps and the augmentation system are the model’s ramp schedule. Augmentation is blank in year 1, and from year 14 the sheet follows the feddans. Delivered water is the P&L series: Lake Nasser through year 24, seawater desalination from year 25. The old-valley bar is complete in year 13.

Year

2034

202720522076

Pipes

3,500 km

Working pumps

52

Augmentation

52

Augmentation power

200 MW

Lake Nasser

29.4 bn m³

Seawater desalination

0.00 bn m³

Old valley, modern

62%

Delivered water

29.4 bn m³

Egyptian Mega Agriculture Corporation

National platform, not a farm

The project company builds conveyance, irrigation and land readiness. Lessees cultivate wheat, maize, cotton, sugar beet and soybean. Company cash flow is infrastructure income, not commodity trading.

Two contracted streams

Euro charges through Year 15. From Year 16, the equivalent amount in Egyptian pounds. Royalty fixed at 8%.

01

Volumetric water charge

Primary cash engine. Charged per cubic metre delivered. Core income of the infrastructure company.

02

8% crop royalty + land lease

Fixed 8% of crop sale value. The same lines are framed as land-lease income. Crop proceeds stay with lessees.

The company owns

Pipelines, pumps, treatment, land rights and community systems. All modelled capex is water-system capex.

Held by lessees

Standing crop, inventory and offtake. Lessees fund cultivation, harvest, storage and sale.

Four parties

Project company

Owns water infrastructure and land rights. Collects charges, royalty and lease. Funds construction, operations and localisation.

Youth co-ops & farms

Lease prepared land. Cultivate and sell the five-crop mix. Keep crop proceeds; pay water, royalty and lease.

Sovereign Fund

Contributes land and rights. Receives an ongoing share from Year 2.

Equity & lenders

Owner draws and third-party equity from the ramp. Debt is staged against the pipe schedule.

National assessment

Recommended for Presidential Decree

Strategic importance

Excellent

Revenue model

Sound

Technical feasibility

Good

Cash-flow trajectory

Strong

Capital programme

Sovereign scale

Currency after Year 15

EGP equivalent

Construction analogue

Libya’s Great Man-Made River — how desert pipe is made, hauled and laid. Not this project’s sites, contracts or costs.

Pipe plants — Sarir and Brega, analogue
Pipe haul on desert roads
Pipe laying — trench and crane, analogue

Feasibility study G · September 2026. Planning figures. Validate before capital commitment.